MWITA-CI-2026-010 · Evidence A · P0
The same official review placed Casablanca's 300-million-cubic-metre desalination project at about 81% completion for its 200-million-cubic-metre first phase and scheduled service for 1 February 2027; it was not operating in 2025.
What this does not establish
The project's full 300 million cubic metres must not be added to operating stock.
Counterevidence & uncertainty
Schedule and final scope may change before acceptance testing.
What would change the reading
Require official commissioning and production evidence after February 2027.